臥式泡沫泵軸承的安裝
臥式泡沫泵軸承的安裝步驟如下:
1. 準(zhǔn)備工作:檢查軸承型號(hào)、規(guī)格、數(shù)量是否符合設(shè)計(jì)要求,檢查軸承內(nèi)外圈、滾珠和保持架是否完好無(wú)損。
2. 清洗:將軸承放入清洗油中浸泡一段時(shí)間,用清潔布擦拭干凈表面的污垢和銹跡。
3. 安裝軸承座:將軸承座放在基礎(chǔ)上,用螺栓固定好,確保軸承座與基礎(chǔ)之間有足夠的間隙以便安裝軸承。
4. 安裝軸承:將軸承放在軸承座上,用專用工具(如壓力機(jī))將軸承壓入軸孔中,注意不要過(guò)緊或過(guò)松,以免損壞軸承。
5. 安裝滾珠和保持架:將滾珠放入軸承內(nèi)圈的凹槽中,然后將保持架放在滾珠周圍,確保滾珠能夠自由滾動(dòng)而不卡住。
6. 調(diào)整游隙:用手輕輕轉(zhuǎn)動(dòng)軸承,檢查其是否能自由旋轉(zhuǎn)且無(wú)明顯的晃動(dòng)現(xiàn)象。如果發(fā)現(xiàn)軸承游隙過(guò)大或過(guò)小,可以通過(guò)調(diào)整軸承外圈的凸起部分來(lái)實(shí)現(xiàn)。
7. 安裝聯(lián)軸器:將聯(lián)軸器與電機(jī)連接好,并將其固定在設(shè)備上。
8. 測(cè)試運(yùn)行:?jiǎn)?dòng)設(shè)備,觀察軸承的工作狀態(tài)和噪音情況,如有問(wèn)題及時(shí)處理。
Installation of horizontal foam pump bearing
The installation steps of horizontal foam pump bearings are as follows:
1. Preparation: Check whether the bearing model, specification, and quantity meet the design requirements, and whether the inner and outer rings, balls, and cages of the bearing are intact.
2. Cleaning: Soak the bearing in cleaning oil for a period of time, and wipe off any dirt and rust on the surface with a cleaning cloth.
3. Installation of bearing seat: Place the bearing seat on the foundation and fix it with bolts to ensure sufficient clearance between the bearing seat and the foundation for bearing installation.
4. Install the bearing: Place the bearing on the bearing seat and use a special tool (such as a press) to press the bearing into the shaft hole, taking care not to be too tight or too loose to avoid damaging the bearing.
5. Install the ball and cage: Place the ball into the groove of the bearing inner race, and then place the cage around the ball to ensure that the ball can roll freely without getting stuck.
6. Adjust the clearance: Gently rotate the bearing by hand to check if it can rotate freely without obvious shaking. If the bearing clearance is found to be too large or too small, it can be achieved by adjusting the protruding part of the bearing outer ring.
7. Install the coupling: Connect the coupling to the motor and fix it on the equipment.
8. Test run: Start the equipment, observe the working status and noise situation of the bearings, and promptly handle any problems.